HDD Projects Reference List

No Project Pipes' Diameter Pipes' Material Length Period of Execution Year
1 Suez Canal Crossing No.1:
Water pipe under Suez Canal, Railway, West Road, Ismailia - Port Said Canal and East Road, with 40 m depth from water level.
36 inch H.D.P.E 640 m 30 Days 1998
2 Suez Canal Crossing No.2:
Water pipe under Suez Canal, Railway, West Road, Ismailia - Port Said Canal and East Road, with 40 m depth from water level.
36 inch H.D.P.E 640 m 30 Days 1998
3 Suez Canal Crossing No.3:
Water pipe under Suez Canal, Railway, West Road, Ismailia - Port Said Canal and East Road, with 40 m depth from water level.
36 inch H.D.P.E 640 m 30 Days 1999
4 Suez Canal Crossing No.4:
High Pressure Gas pipe, with 40 m depth, under Suez Canal, Port Said - Ismailia Desert Road, Ismailia Canal, Railway, West Road and East Road.
36 inch Steel coated 1200 m 30 Days 1999
5 Suez Canal Crossing No.5:
High Pressure Gas pipe, with 40 m depth, under Suez Canal, Port Said - Ismailia Desert Road, Ismailia Canal, Railway, West Road and East Road.
36 inch Steel coated 1200 m 30 Days 1999
6 Suez Canal Crossing No.6:
3 collected High Pressure Gas pipe, with 40 m depth under Suez Canal, Port Said - Ismailia Desert Road, Ismailia Canal, Railway, West Road and East Road.
1x16 inch
2x12 inch
Steel coated 1200 m 30 Days 1999
7 Suez Canal Crossing No.7:
6'' Steel Sleeve pipe under Suez Canal with 40 m depth for laying fiber optics telephone cables.
6 inch Steel coated 750 m 10 Days 2001
8 Suez Canal Crossing No.8:
28'' Water pipe under Suez Canal, with 41 m depth beside Ahmed Hamdy Tunnel at Km 142.850.
28 inch H.D.P.E 680 m 30 Days 2002
9 Suez Canal Crossing No.9:
28'' Water pipe under Suez Canal, with 41 m depth beside Ahmed Hamdy Tunnel at Km 142.865.
28 inch H.D.P.E 680 m 30 Days 2002
10 Suez Canal Crossing No.10:
Power Cables inside 12'' pipe under Suez Canal, Railway, Road and Canal with 40 m depth close to Port Said.
12 inch H.D.P.E 597 m 15 Days 2002
11 Suez Canal Crossing No.11:
Power Cables inside 12'' pipe under Suez Canal, Railway, Road and Canal with 40 m depth close to Port Said.
12 inch H.D.P.E 598 m 15 Days 2002
12 Suez Canal Crossing No.12:
Power Cables inside 12'' pipe under Suez Canal, Railway, Road and Canal with 40 m depth close to Port Said.
12 inch H.D.P.E 598 m 15 Days 2002
13 Suez Canal Crossing No.13:
Power Cables inside 12'' pipe under Suez Canal, Railway, Road and Canal with 40 m depth close to Port Said.
12 inch H.D.P.E 598 m 15 Days 2002
14 Suez Canal Crossing No.14:
Power Cables inside 12'' pipe under Suez Canal, Railway, Road and Canal with 40 m depth close to Port Said.
12 inch H.D.P.E 597 m 15 Days 2002
15 Suez Canal Crossing No.15:
Power Cables inside 12'' pipe under Suez Canal, Railway, Road and Canal with 40 m depth close to Port Said.
12 inch H.D.P.E 596 m 15 Days 2002
16 Suez Canal Crossing No.16:
Power Cables inside 12'' pipe under Suez Canal, Railway, Road and Canal with 40 m depth close to Port Said.
12 inch H.D.P.E 599 m 15 Days 2002
17 Suez Canal Crossing No.17:
Power Cables inside 12'' pipe under Suez Canal, Railway, Road and Canal with 40 m depth close to Port Said.
12 inch H.D.P.E 596 m 15 Days 2002
18 Suez Canal Crossing No.18:
Power Cables inside 12'' pipe under Suez Canal, Railway, Road and Canal with 40 m depth close to Port Said.
12 inch H.D.P.E 597 m 15 Days 2002
19 Suez Canal Crossing No.19:
Power Cables inside 12'' pipe under Suez Canal, Railway, Road and Canal with 40 m depth close to Port Said.
12 inch H.D.P.E 597 m 15 Days 2002
20 Suez Canal Crossing No.20:
Power Cables inside 12'' pipe under Suez Canal, Railway, Road and Canal with 40 m depth close to Port Said.
12 inch H.D.P.E 598 m 15 Days 2002
21 Suez Canal Crossing No.21:
Power Cables inside 12'' pipe under Suez Canal, Railway, Road and Canal with 40 m depth close to Port Said.
12 inch H.D.P.E 597 m 15 Days 2002
22 Suez Canal Crossing No.22:
Power Cables inside 12'' pipe under Suez Canal, Railway, Road and Canal with 40 m depth close to Port Said.
12 inch H.D.P.E 597 m 15 Days 2002
23 Suez Canal Crossing No.23:
Power Cables inside 12'' pipe under Suez Canal, Railway, Road and Canal with 40 m depth close to Port Said.
12 inch H.D.P.E 598 m 15 Days 2002
24 Suez Canal Crossing No.24:
Two Fiber Optics Cables inside 12'' pipe under Suez Canal, Railway, Road, Canal with 40 m depth close to Port Said.
12 inch H.D.P.E 597 m 15 Days 2002
25 Suez Canal Crossing No.25:
10'' Water pipe under Suez Canal, Railway, West Road, Ismailia - Port Said Canal, and East Road, with 40 m depth from water level at Km 137.300.
10 inch H.D.P.E 676 m 21 Days 2004
26 Suez Canal Crossing No.26:
10'' Water pipe under Suez Canal, Railway, West Road, Ismailia - Port Said Canal, and East Road, with 40 m depth from water level at Km 90.200.
10 inch H.D.P.E 642 m 15 Days 2004
27 Suez Canal Crossing No.27:
24'' Water pipe under Suez Canal, Railway, West Road and East Road, with 40 m depth from water level at Km 47.860.
24 inch H.D.P.E 628 m 15 Days 2004
28 Suez Canal Crossing No.28:
24'' Water pipe under Suez Canal, Railway and Road with 32.4 m depth from water level at Km 3.900 Raswa.
24 inch H.D.P.E 742 m 30 Days 2004
29 BTC Agsu Canal Crossing:
42'' Gas pipeline under Agsu Canal in Azerbaijan.
42 inch Steel coated 535 m 20 Days 2004
30 SCP Agsu Canal Crossing:
42'' Gas pipeline under Agsu Canal in Azerbaijan.
42 inch Steel coated 535 m 15 Days 2004
31 BTC Karabkh Canal Crossing:
42'' Gas pipeline under Karabakh Canal in Azerbaijan.
42 inch Steel coated 651 m 20 Days 2004
32 SCP Karabkh Canal Crossing:
42'' Gas pipeline under Karabakh Canal in Azerbaijan.
42 inch Steel coated 662 m 15 Days 2004
33 SCP Karabkh Canal Crossing:
42'' Gas pipeline under Karabakh Canal in Azerbaijan.
42 inch Steel coated 703 m 20 Days 2004
34 SCP Chinny Village Crossing:
42'' Gas pipeline under Chinny Village in Azerbaijan.
42 inch Steel coated 514 m 15 Days 2004
35 SCP Qurabyork Village Crossing:
42'' Gas pipeline under Qurabyork in Azerbaijan.
42 inch Steel coated 1003 m 45 Days 2004
36 Suez Canal Crossing No.29:
6'' Fuel pipe under Suez Canal, with 43.50 m depth from water level at Km 73.300.
6 inch Steel coated 700 m 15 Days 2004
37 Suez Canal Crossing No.30:
Power Cables inside four 10'' HDPE sub-duct inside 24'' HDPE pipe under Suez Canal, Railway and Road with 31.5 m depth from water level at Km 3.900 Raswa.
24 inch H.D.P.E 735 m 30 Days 2004
38 Suez Canal Crossing No.31:
6'' Fuel pipe under Suez Canal, with 40.00 m depth from water level at Km 133.750.
6 inch Steel coated 707 m 19 Days 2005
39 Suez Canal Crossing No.32:
24'' Water pipe under Suez Canal, Railway, West Road and East Road, with 44.55 m depth from water level at Km 47.850.
24 inch H.D.P.E 645 m 30 days 2005
40 Suez Canal Crossing No.33:
6'' Fuel pipe under Suez Canal, West Road and East Road with 40.56 m depth from water level at Km 89.900.
6 inch Steel coated 642 m 18 days 2005
41 Suez Canal Crossing No.34:
6'' Fuel pipe under Suez Canal and Road with 40.0 m depth from water level at Km 148.600.
6 inch Steel coated 633 m 13 days 2005
42 Suez Canal Crossing No.35:
6'' Fuel pipe under Suez Canal, Railway, West Road and East Road with 40.0 m depth from water level at Km 50.200.
6 inch Steel coated 665 m 17 days 2005
43 Suez Canal Crossing No.36:
10'' Water pipe under Suez Canal, Railway, West Road and East Road with 42.43 m depth from water level at Km 47.550.
6 inch H.D.P.E 698 m 15 days 2005
44 Suez Canal Crossing No.37:
10'' Water pipe under Suez Canal and Road with 40.0 m depth from water level at Km 149.00.
6 inch H.D.P.E 636 m 13 days 2005
45 Suez Canal Crossing No.38:
24'' Water pipe under Suez Canal, Railway, West Road and East Road, with 44.55 m depth from water level at Km 47.850.
24 inch H.D.P.E 625 m 30 days 2005
46 Suez Canal Crossing No.39:
Power Cables inside 12'' pipe under Suez Canal, Railway, West Road, Canal and East Road, with 40.86 m depth from water level at km 43.433.
12 inch H.D.P.E 717 m 12 days 2005
47 Suez Canal Crossing No.40:
Power Cables inside 12'' pipe under Suez Canal, Railway, West Road, Canal and East Road, with 41.46 m depth from water level at km 43.430.
12 inch H.D.P.E 720 m 12 days 2005
48 Suez Canal Crossing No.41:
Power Cables inside 12'' pipe under Suez Canal, Railway, West Road, Canal and East Road, with 40.97 m depth from water level at km 43.427.
12 inch H.D.P.E 722 m 11 days 2005
49 Suez Canal Crossing No.42:
Power Cables inside 12'' pipe under Suez Canal, Railway, West Road, Canal and East Road, with 41.26 m depth from water level at km 43.424.
12 inch H.D.P.E 721 m 8 days 2005
50 Suez Canal Crossing No.43:
Power Cables inside 12'' pipe under Suez Canal, Railway, West Road, Canal and East Road, with 40.16 m depth from water level at km 43.421.
12 inch H.D.P.E 722 m 8 days 2005
51 Suez Canal Crossing No.44:
Power Cables inside 12'' pipe under Suez Canal, Railway, West Road, Canal and East Road, with 40.96 m depth from water level at km 43.418.
12 inch H.D.P.E 722 m 8 days 2005
52 Suez Canal Crossing No.45:
Power Cables inside 12'' pipe under Suez Canal, Railway, West Road, Canal and East Road, with 41.66 m depth from water level at km 43.415.
12 inch H.D.P.E 722 m 8 days 2005
53 Blue Nile River Crossing:
32'' Gas pipeline under Blue Nile River in Sudan.
32 inch Steel coated 640 m 30 days 2005